1.4M patients, one launch date that didn't move
01 / Context
A multi-state hospital network’s consumer-facing mobile app and go-to-market strategy for Epic MyChart integration, across a four-state Southern market (Georgia, Kentucky, Tennessee, Texas) — a healthcare system serving 1.4M+ portal users.
02 / Problem
The contract was $205K. The work became $750K.
A multi-workstream project — UX design, analytics, competitive analysis, launch comms — grew well past its original scope mid-flight, with a fixed app-store launch date (May 28th) that couldn’t move. Separately, the content team was integrating an LLM with no agreed usage policy, security review, or operational workflow yet in place.
03 / Approach
Put governance in place immediately, then make room for the scope that already existed.
04 / What I did
Managed delivery of the enhanced content strategy and blog experience end to end — design, analytics, and SEO coordinated for one storyline. Built the go-to-market strategy itself: messaging framework, audience segmentation across 5 patient segments, multi-channel plan across internal and external touchpoints.
Managed technical integration planning for app store analytics, Epic MyChart customization, and consumer identity architecture, while coordinating parallel video production and legal review.
Role: Sr. Technical Project Manager · Digital agency (client: hospital network) · Mar–Nov 202505 / Outcome
Shipped on the May 28th app store deadline despite the 3.7x scope growth, with formal governance (RACI, weekly reporting) holding 20+ stakeholders across two organizations aligned the whole way. The LLM governance work landed alongside it — usage policy, security, and operational workflow agreed before the content team scaled its use.
06 / What I would do differently
The $205K → $750K growth wasn’t a surprise in hindsight — it was scope that should have been priced in from the first discovery conversation. I’d push harder up front for a phased SOW instead of absorbing the delta mid-project.